Who is actually building the grid
Updated 2026-11-13 · checked against the sources below
Ask who builds Ireland's electricity grid and most people will name the two system operators. The planning register gives a different answer. We read every planning application for grid works since 2019 and recorded who is behind each one. For every application lodged by a system operator, more than six are lodged by a developer. Grid Elder's paper on Irish solar puts the consequence plainly: operators carry the duty to keep the system reliable, yet must depend on external commercial appetite to get much of it built. This is a count of that dependence. The counts are read from the PlanningLeads record when the page is built.
The count
We hold 1,337 planning applications for electricity grid works: lines, cables, substations and the grid works attached to generation and storage. Each is classed by the kind of organisation behind it.
| Who is behind it | Applications | Share | Live now |
|---|---|---|---|
| Developers and independent generators | 747 | 56% | 447 |
| Industrial and commercial businesses | 359 | 27% | 258 |
| Public bodies | 58 | 4% | 43 |
| System operators | 96 | 7% | 77 |
| Data centres | 18 | 1% | 8 |
| Not stated on the application | 59 | 4% | 42 |
Operators build the lines. Developers build nearly everything else
The split is sharper by type of work. Of 44 overhead line applications, 38 came from a system operator. Of 101 underground cable applications, 86 came from developers, typically to connect a generation or storage project to a substation some distance away. Of 881 applications for a new substation, 25 came from an operator.
Measured in route length the operators still lead: their applications state 877 km of line and cable, against 395 km for developers. So the backbone is operator work, and the capillaries are private. A developer's cable or substation is built to operator standards and may be handed over, but the planning risk, the land and the timing are the developer's.
Two groups stand out. 389 applications are for generation or storage with its own grid works, and 367 of those are from developers. And of 76 substations built to connect a single customer, 13 are for data centres.
Is it becoming plan-led?
Policy has moved from a market-led grid towards a plan-led one, in which the State and the operators decide where capacity goes. If that shift were showing in planning, the operators' share of applications would be rising. It is not yet. Operators lodged 13 of 128 grid applications received in 2023, 27 of 262 in 2024, 30 of 363 in 2025 and 18 of 348 so far in 2026. Their numbers have doubled. Their share has not risen: it was about one in ten in 2023 and 2024 and has been lower since, because private applications grew faster.
That fits what Grid Elder writes about the solar and storage wave: that it has been commercially adroit, private capital funding its own balancing assets while the wider network waited. The register shows the same thing in a different unit, as it does for solar farms and the batteries beside them. The grid Ireland is building this decade is, by count of projects, mostly being built from the outside in.
The public side: tenders
Operator work shows up more clearly in procurement than in planning. We hold 118 public tenders for grid works, supply and services, 34 published in 2025 and 41 so far in 2026. ESB accounts for 40 and EirGrid for 11, with the HSE, Irish Rail and others buying substations and connections for their own sites. 27 awards carry a published value, EUR 595 million in total. Across the awarded grid tenders we count 59 winning firms. Our guide to how many bids an Irish public tender gets covers the competition for them.
What the count cannot say
An application is not a megawatt or a kilometre, and a small unit substation counts the same as a 110 kV station. On 59 applications the kind of applicant is not stated. Works that are exempt from permission, which includes much routine operator work, never reach the register. And the register is deep only from 2019. The count shows who is asking for permission to build, which is not the whole of who is building. For how long those permissions take, see how long a wire takes in planning.
If your work depends on who is building
For a contractor or supplier this split is the market. The private grid works are more numerous, less visible and not bought through public tenders, so the planning register is where they first appear. PlanningLeads lists each with its applicant organisation, agent, stage and nearest station, and the public tenders sit beside them with the winner named after award. Basic is free at county level. Pro adds full addresses, the map layers and alerts for new grid applications in your counties.
See the private grid works before they are priced
Cables, substations and connections by applicant organisation, stage and council, with public grid tenders beside them. Basic is free at county level.
See PlanningLeads for utilitiesQuick answers
Who builds the electricity grid in Ireland?
The system operators build and own the network, but most planning applications for grid works are lodged by others. On the PlanningLeads record, developers and independent generators lodged 747 of 1,337 grid applications and the system operators lodged 96.
Why do developers build grid connections?
A generator, battery or large customer often has to build the cable or substation that connects its own project. The works are built to the operator's standards, but the developer applies for the permission and carries the planning risk.
How many grid tenders are published in Ireland?
We hold 118 public tenders for grid works, supply and services, with 41 published so far in 2026. 27 awards carry a published value, EUR 595 million in total.