Coolnabacky is the extreme, not the exception

Updated 2026-11-13 · checked against the sources below

Grid Elder has a name for the Laois Kilkenny reinforcement: a 400 kV odyssey. First planned in 2008, permitted in 2014, blockaded, reviewed, begun in 2023 and due to be commissioned in 2027. Nineteen years for the first new connection into the southern 400 kV line. It is a story that sounds too bad to be typical, so we checked it against the transmission programme that EirGrid and ESB Networks publish each quarter, which we hold project by project and join to the planning record. Two things came out. His dates are right. And Coolnabacky is the far end of a pattern, not a one-off. The programme figures are read from the edition we hold when the page is built, at present the one for the second quarter of 2026. Coolnabacky's own dates were read from the programme on 13 November 2026.

19.4 years
Coolnabacky, approval to energisation
April 2008 to September 2027
6.4 years
Typical transmission project
279 projects with both dates
9.9 years
Typical 400 kV project
one in ten takes over 16.6

The record on Coolnabacky

The project is on the programme as CP0585, the Laois Kilkenny (Coolnabacky) 400 kV station with its lines and station works. Capital approval is dated 16 April 2008. Final energisation is now given as 17 September 2027, moved in the latest edition from a baseline of 30 June 2027. That is 19.4 years from approval to energisation, the longest of any project on the programme with both dates.

It is not alone at that end of the table. The refurbishment of the Louth 220 kV station runs 19.3 years from approval to its current date. The Finglas 110 kV station redevelopment runs 17.1 years. The North South interconnector was approved in 2016, has not yet reached its Project Agreement, and carries a date of 2031.

How long a transmission project really takes

The programme lists 535 projects, 405 of them inside the current five year price review. 279 have both an approval date and a final energisation date.

Two readings stand out. The higher the voltage, the longer it takes: a 400 kV project typically needs a decade. And the work the system needs for itself is slower than the work a customer pays for. A customer connection takes 4.3 years. A reinforcement takes 7.5 years. That matters because most grid applications come from customers, not operators.

The time is not mainly construction: the typical project spends 1.9 years between approval and its Project Agreement, the point at which ESB Networks procures and builds, and 3.8 years from there to final energisation.

Kind of projectProjects with both datesTypical timeSlowest tenth
All projects2796.4 yearsover 10.3 years
System reinforcement1167.5 yearsover 10.6 years
Asset refurbishment707.1 yearsover 12.7 years
Customer connection404.3 yearsover 7.0 years
110 kV1755.7 yearsover 8.7 years
220 kV797.5 yearsover 12.6 years
400 kV169.9 yearsover 16.6 years
Approval to final energisation, transmission programme, second quarter of 2026 Typical time is the median. The programme states that every date is indicative.

Are the dates holding?

210 projects carry both a baseline date and a current one. 109 are unchanged. 27 have moved earlier. 74 have moved later, and 39 of those by more than a year. In the latest edition alone, 138 projects had a date updated.

That is a better record than the odyssey suggests, and it is fair to the people delivering the programme to say so. Most dates are holding. But the ones that slip, slip by years, and they tend to be the large reinforcements that everything else waits on.

What is due by 2030

Grid Elder's question about the next price review is whether a network that spent about EUR 7.5 billion in five years can spend EUR 14 billion, or EUR 19 billion in the high case, in the next five. The programme gives one way to look at it.

199 projects are dated to finish by the end of 2030. 77 are already dated after it. 129 have no date at all, most of them before their Project Agreement. If a project typically takes 3.8 years from that agreement to energisation, one that has not reached it by early 2027 is unlikely to energise in this decade.

The work is concentrated where the demand is, in the counties where solar farms and data centres are waiting on capacity: by number of projects, Cork (66), Dublin (63), Kildare (59) and Meath (51).

Final energisationProjects
202637
202759
202846
202933
203024
After 203077
No date yet129
Projects in the price review by year of final energisation

What we take from it

We keep a planning record. We are not an engineering authority, and on what the system needs we defer to those who ran it. What the record can add is scale. Coolnabacky took nineteen years, and the typical reinforcement takes seven and a half. Both numbers argue for what Grid Elder asks for: a realistic plan, and a planning system that lets it be built.

The planning stage is only part of that time. Our companion piece on how long a wire takes in planning shows that the decision itself is usually a matter of weeks or months, and that the years come from what surrounds it.

Following the programme

Every project on the programme is on PlanningLeads beside the planning applications, strategic cases, tenders and stations it relates to. A contractor can see which reinforcements have just signed a Project Agreement. A developer can see what is planned at the station their project depends on, and when. Basic is free at county level, and the programme view is on the paid plans.

Follow the transmission programme project by project

Each programme project beside the planning applications, tenders and stations it relates to. Basic is free at county level.

See PlanningLeads for utilities

Quick answers

How long does a transmission project take in Ireland?

On the delivery programme for the second quarter of 2026, the typical project takes 6.4 years from capital approval to final energisation, across 279 projects with both dates. One in ten takes more than 10.3 years.

When will the Coolnabacky 400 kV station be finished?

The programme gives final energisation as 17 September 2027. Capital approval was in April 2008. The programme states that all dates are indicative.

Do higher voltage projects take longer?

Yes: the typical 110 kV project takes 5.7 years from approval to energisation, a 220 kV project 7.5 years and a 400 kV project 9.9 years.

How many transmission projects are due by 2030?

Of 405 projects in the current price review, 199 are dated to reach final energisation by the end of 2030, 77 are dated later and 129 have no date yet.