Solar farms in Ireland: what the planning register adds to The Accidental Surge

Updated 2026-11-13 · checked against the sources below

Grid Elder's paper, Solar Power in Ireland: The Accidental Surge (7 October 2026), is the clearest account we have read of why Ireland built a solar fleet in a cloudy climate. Its argument is that Irish solar is an economic response to high retail prices and a slow grid, not a gift of the weather, and that battery storage is now the condition for building more of it. It is the work of a former chief engineer, and it is strongest where it describes how the system behaves at midday in May and at six in the evening in January. We keep a different kind of record: every planning application in the State, sorted by project type, stage and place. So we read the paper with one question. What does the planning register say about the same story? It agrees with the paper on every point it can test, and it adds a few things only the register can see. The counts below are read from the PlanningLeads record when the page is built. Figures for a single past year, and the paper's own, are as they stood on 13 November 2026.

234
Solar farms granted, not started
64 more are in planning
35
With a commencement notice
consent is outrunning connection
14%
Solar farm applications that mention a battery
7.5% in 2023, 18.2% in 2025

Where the register agrees with the paper

The pipeline is real. The paper's forward scenarios take solar from 2.7 GW today to between 5 and 8 GW. On the planning side that supply already exists: 234 solar farms have permission and have not started, and 64 more are in planning. The auction record points the same way: we hold 60 solar projects from RESS rounds 3 to 5, totalling 2,311 MW, each tied back to its planning permission where one can be matched.

The constraint is the grid, not the permission. Grid Elder describes transmission expansion as glacial and names connection queues and substation capacity as the limits. The register shows the same thing from the other end. Against 234 granted solar farms, only 35 have a commencement notice on the register. The permissions are recent too: 176 of the 234 were granted since the start of 2025. Developers are getting consent faster than they can get connected. We have since counted how long a wire takes in planning and how long transmission projects take to deliver.

Storage is arriving, as the paper says it must. Applications that include battery storage numbered 11 in 2023, 43 in 2024, 56 in 2025 and 77 so far in 2026. Our record grew over that period, but as a share of all applications that is still roughly a threefold rise.

Most solar is still unbuffered. This is the paper's central warning, and the register puts a number on it. Only 14% of solar farm applications mention a battery. The share is rising, from 7.5% of those received in 2023 to 18.2% in 2025, but it is far from the norm. Of the 177 substations that are the nearest station to a live solar project, 137 have no battery application near them. The paper's first recommendation, to couple storage with future auction rounds, is aimed at exactly this gap.

What the paper arguesWhat the planning register shows
Solar can reach 5 to 8 GW by 2030234 solar farms granted and not started, 64 in planning
Grid delivery is the bottleneck35 commencement notices against 234 grants; 176 of those grants date from 2025 or later
Storage must accompany solarBattery storage applications: 11, 43, 56 and 77 a year from 2023 to 2026
Unbuffered solar is the risk14% of solar farm applications mention a battery
Auctions anchor ground-mount solar60 solar projects in RESS rounds 3 to 5, 2,311 MW
The paper's argument beside the planning record Counts are planning applications, not sites or megawatts connected. 2026 is the year to date.

What the register adds

Planning is a filter too. The paper's list of bottlenecks is an engineer's list, and rightly so. The register adds a planner's one. Councils have refused 33 solar farms, 17 of them in 2025. One application in ten is appealed. In An Coimisiún Pleanála's renewables case list, solar stands at 27 grants and 16 refusals. A scheme that clears the grid queue still has to clear this one. Our guide to how long an appeal takes has the timings.

Where it is being built. The paper warns of local voltage problems in solar-dense regions. The register says where those are. Live solar farms are concentrated in Wexford (40), Cork (38), Meath (19), Kilkenny (18) and Tipperary (17).

How much land. 350 solar farm applications state a site area. Together they cover 14,621 hectares, an average of 42 hectares each. Land is the one input the paper does not discuss, and it is the one neighbours and councils discuss most.

How long it takes, and how long it lasts. A granted solar farm took 17 weeks on average from receipt to decision. Permission is not open-ended: 14 granted schemes will lapse within 24 months if work does not begin. For a project waiting on a connection offer, that clock matters.

The rooftop story, seen sideways. Grid Elder puts rooftop solar above 800 MW and credits planning exemptions for part of that. Those exemptions are also why rooftop solar is nearly invisible to any planning record, ours included. What we do see is the commercial arrays large enough to need permission: 857 applications on 13 November 2026, 465 of them live now. And we see the roofs to come. Our rooftop estimate across 113,636 live building projects sums to 1,046 GWh a year. At the paper's own yield of about 900 kWh per kilowatt, that is in the region of 1.1 GW of roof potential on buildings that are not yet finished.

What a planning record cannot see

A planning record has limits, and it is fair to state them. Ours is deep from 2019 onward, so the earlier wave of solar permissions is missing. A commencement notice is not the same thing as an energised connection, and some solar farms may start without one reaching the register. We count applications, so a scheme that was withdrawn and lodged again appears twice in the totals, though only once among live projects.

Prices, tariffs and system operation, the heart of Grid Elder's analysis, are outside the register altogether. On those we defer to the paper.

Who this is useful to

If the paper is right, and we think it is, the next few years of Irish solar will be decided project by project: which schemes have consent, which have a grid offer, which add a battery, and which run out of time. That is what the register tracks, and it is what PlanningLeads for solar is built on.

  • Developers and land agents can see who has applied where, which councils grant, and which areas are already crowded.
  • Storage developers can find the solar farms and substations with no battery beside them.
  • EPC, electrical and civil contractors can follow a scheme from application to grant to commencement, with the applicant company and agent named.
  • Grid contractors and suppliers can see 388 live grid works beside the substations and lines they relate to.
  • Funders, advisers and analysts can test a pipeline claim against the permissions that exist.

With thanks

Our thanks to Grid Elder for a paper that gave us something worth checking our data against. If he or any reader would like the figures behind this piece, or a cut for one county, write to info@planningleads.ie.

Follow solar and storage from application to site

Basic is free and covers every council at county level. Pro opens full addresses, saved alerts for new solar and battery storage applications, the map layers and Market insights.

See PlanningLeads for solar

Quick answers

How many solar farms have planning permission in Ireland?

The PlanningLeads record holds 234 solar farm applications that are granted and have not started, 64 awaiting a decision and 35 with a commencement notice on the register. The record is deep from 2019 onward, so earlier permissions are not counted.

Why have so few granted solar farms started?

The planning register does not record the reason. Grid Elder's paper names connection queues and substation capacity as the limits, and the pattern on the register fits that: most of the permissions are recent, and starts trail grants by a wide margin.

How many Irish solar farms include battery storage?

14% of solar farm applications on the record mention a battery or energy storage. The share was 7.5% of those received in 2023 and 18.2% of those received in 2025.

Does rooftop solar need planning permission?

Mostly no. Rooftop solar on homes and most other buildings is exempt, which is why it barely appears on the planning register. Our homeowner guide to the solar panel rules sets out the exemptions and their limits.

Where are solar farms being built in Ireland?

Live solar farm applications are most numerous in Wexford, Cork, Meath, Kilkenny and Tipperary.

Sources

Related

Figures are counts from public registers, read when this page was last built, and they move weekly. They describe the register, not any named organisation, and they are not legal, planning or procurement advice. Check the sources above before you rely on a number.