Guide for the trade
How long a wire takes in planning
Updated 2026-11-13 · checked against the sources below
Grid Elder's paper on Irish solar ends on a plea that is hard to argue with: the grid is the limit, and the country has to be able to build wires. It is fair to ask how much of the delay is planning. We hold every planning application for grid works that has reached a council register since 2019, and every strategic grid case at An Coimisiún Pleanála, so we counted. The answer is more interesting than fast or slow. The decision itself usually takes weeks. The years come from what happens around it. The figures are read from the PlanningLeads record when the page is built.
The decision is quick. The questions are not
We hold 1,337 planning applications for electricity grid works: lines, cables, substations and the grid works attached to generation and storage. Of the 825 granted with both dates on the register, the typical one was decided 8 weeks after it was received. That is the statutory period, met.
The average hides the spread. One granted application in ten took more than 38.3 weeks. The reason is nearly always a request for further information. 297 of the granted applications had one, and their median was 25 weeks. The 528 without one had a median of 7.7 weeks. A further information request triples the time, and for grid works it comes in more than a third of cases.
| Type of work | Granted applications | Typical time to decision | Route length stated |
|---|---|---|---|
| Overhead line | 33 | 8 weeks | 690 km across 32 applications |
| Underground cable | 38 | 20 weeks | 383 km across 53 applications |
| New substation | 567 | 9 weeks | not applicable |
| Substation extension or upgrade | 51 | 8 weeks | not applicable |
Cables take longer than lines
It is usually assumed that an overhead line is the hard thing to permit and a cable the easy one. At council level the register says the opposite. Underground cable applications took 20 weeks to decide, against 8 for overhead lines. Cables run along public roads, and the questions about road openings, traffic and other services tend to arrive as further information requests.
There is a caution. Only 44 overhead line applications reached a council register in this period, against 101 for cables. The contested overhead lines are large enough to go straight to the Commission as strategic infrastructure, so the council figures describe the smaller ones.
One in six is appealed, and an appeal adds half a year
Councils refused 115 of the 1,337 applications, about one in twelve. 222 were appealed, about one in six. An appeal took 24 weeks from lodging to decision on the 159 that have been decided, and one in ten took more than 67.6 weeks. That is in line with appeal times across all development.
The appeal rate is not falling. Of grid applications received in 2023, 32 of 128 were appealed. For 2024 it was 56 of 262, and for 2025 it is 82 of 363 so far.
Strategic cases: nine months, with a long tail
The largest grid works do not go to a council at all. We hold 155 strategic grid cases at An Coimisiún Pleanála. Of the 116 decided, the typical one took 9 months from lodging, and one in ten took more than 20.7 months. Network projects took 10 months. Generation and storage projects with grid works attached took 13 months.
The outcome is rarely a refusal: 106 were granted, 5 refused and 1 quashed, with 39 still in progress. The caseload is growing. 17 cases were lodged in 2023, 18 in 2024, 22 in 2025 and 31 so far in 2026.
What this says about the plea to build wires
The planning record supports Grid Elder's argument, with one refinement. A grid project is not slow because a planner takes a long time to decide it. It is slow because of what the decision is wrapped in: the years of route selection before an application is lodged, the further information round, the appeal, and sometimes the courts. Those stages are where reform would bite. The delivery side is in our piece on how long transmission projects take, and the question of who is lodging these applications has its own count.
The record also shows the end of the pipe. Of 828 granted grid applications, 202 have a commencement notice matched to them. We hold 820 commencement notices for grid works in all, many of them for permissions older than our record. Permission is not the last obstacle either. A commencement notice is the first sign on the record that a site is starting.
A planning record has limits. It cannot see pre-application work, judicial review or delivery after a start, and ours is deep only from 2019. Where the paper speaks about system operation and cost, we defer to it.
If you build, supply or fund grid works
Each of these applications is on PlanningLeads with its stage, council, applicant organisation and agent, beside the substation and line it relates to. A contractor can see which schemes have just cleared an appeal. A developer can see how long a council has taken on cable routes like theirs. Basic is free at county level, and Pro adds full addresses, the map layers and alerts when a grid application is lodged, granted or started.
Follow every line, cable and substation through planning
Grid applications by stage, council and applicant organisation, beside the stations and lines they relate to. Basic is free at county level.
See PlanningLeads for utilitiesQuick answers
How long does planning permission for a substation take in Ireland?
On the PlanningLeads record, the typical new substation was decided by its council 9 weeks after receipt, across 567 granted applications. A request for further information roughly triples that.
Do underground cables get planning permission faster than overhead lines?
Not at council level. Underground cable applications took 20 weeks to decide against 8 for overhead lines. The largest overhead lines go to An Coimisiún Pleanála as strategic infrastructure and are not in the council figure.
How often are grid projects appealed?
About one grid application in six is appealed, and a decided appeal took 24 weeks from lodging.
How long does a strategic infrastructure grid case take?
The typical decided case took 9 months from lodging at An Coimisiún Pleanála, and one in ten took more than 20.7 months.
Sources
Related
Figures are counts from public registers, read when this page was last built, and they move weekly. They describe the register, not any named organisation, and they are not legal, planning or procurement advice. Check the sources above before you rely on a number.