110kVWind EnergyGrid & Substations

Development consisting of a new 110kV substation, underground 110kV cabling and ancillary works to connect the already consented Upperchurch Wind Farm substation to the existing 110kV overhead line.

Scale
110kV
Location
Mountphilips, Co. Tipperary
Planning authority
Tipperary County Council
Case type
SID (Not incl LAP SID cases)
Lodged
13 December 2019
Decision
Approve with Conditions · 8 February 2021

Consented under the Strategic Infrastructure Development process by An Coimisiún Pleanála (case 306204). These projects are decided centrally and don't appear in local- authority planning registers.

Win work on projects this size.

PlanningLeads tracks strategic infrastructure alongside every planning application and commencement across all 31 local authorities — scored, sized and filtered to your trade.