110kVGrid & Substations
110kV onsite electrical substation with associated electrical plant, electrical equipment, welfare facilities and waste water holding tank and security fencing. 110kV overhead line grid connection cabling, upgrade of existing tracks and provision of new site access roads with all associated site development and ancillary works.
Scale
110kV
Location
Timahoe East, Co. Kildare.
Planning authority
Kildare County Council
Case type
SID (Not incl LAP SID cases)
Lodged
14 December 2018
Decision
Approve with Conditions · 29 July 2020
Consented under the Strategic Infrastructure Development process by An Coimisiún Pleanála (case 303249). These projects are decided centrally and don't appear in local- authority planning registers.