Planning application · Tipperary County Council

A ten year planning permission for a renewable energy development

Farranrory Upper Farranrory Lower Coolnashinnagh and Gortnasmuttaun, Co. Tipperary

20972 · TipperaryOn Site

Planning application 20972 to Tipperary County Council: A ten year planning permission for a renewable energy development with a 40-year operational life, at Farranrory Upper Farranrory Lower Coolnashinnagh and Gortnasmuttaun. Granted by the council on 24 February 2021. Work commenced on 31 March 2025.

Timeline

  1. Application lodged
  2. Further information requested
  3. Further information received
  4. Council granted
  5. Work commenced

Key facts

Reference
20972
Planning authority
Tipperary County Council
Received
1 Sept 2020
Decided
24 Feb 2021
Status
On Site
Use
Utilities
Floor area
81 m²
Further information requested
22 Oct 2020
Further information received
23 Dec 2020
Commenced
31 Mar 2025

Proposed development

a ten year planning permission for a renewable energy development with a 40-year operational life (from the date of commissioning of the renewable energy development). The entirety of the development constitutes the provision of a 9-turbine wind farm and all associated works on lands in both Counties Tipperary and Kilkenny. This development comprises part of an overall development for which planning permission is also sought for a 38kV substation in the townland of Killeen, Co. Kilkenny. A separate planning application will be made for an underground grid connection to Tipperary County Council and to Kilkenny County Council. The proposed development will constitute the provision of the following: • Construction of up to 9 turbines each with a maximum overall ground to blade tip height of up to 150 metres and associated foundations and hardstand areas; • Construction of new site entrances and upgrade of existing site entrances; • Internal wind farm underground power and communications cabling; • Upgrade of existing access tracks and provision of new site access roads; • Removal of existing Meteorological Masts and construction of 1 new Meteorological Mast for monitoring wind speeds with a maximum height of up to 85 metres; • Site drainage network • Construction of a new temporary site compound for use during construction; • Two Borrow Pits • Construction of a new on-site 38kV substation The planning application will be accompanied by an Environmental Impact Assessment Report (EIAR) and Natura Impact Statement

Planning status

A commencement notice has been lodged: works are under way or about to start.

For the applicant

Is this your application?

Say it is yours and you will see which building firms and trades have asked to work on it, with the contact details they chose to leave. It is free and takes an email address. Nothing is shared with anyone unless you choose to contact them.

Sign in to claim itNo cold calls. Nothing is shared unless you choose to.
Free tool · no account needed

Buying or upgrading a home? Get a free solar, SEAI grant and deep-retrofit report.

Enter an address to see its solar potential, the full SEAI grant it qualifies for, and the BER-uplift economics of a deep retrofit - in one report, in minutes.

Related

About this page: the facts above come from the statutory public planning register kept by Tipperary County Council and are refreshed weekly (last updated 24 Sept 2026). Applicant names and contact details are not shown. Status labels are PlanningLeads' plain-language reading of the register status and the "Use" label is classified by AI from the public description (see how we use AI); neither is legal advice and the council's file is the record. How we handle this data: privacy notice.

Remove my application from this page

If this is your application and you would rather it did not appear here, tell us and we will take the page down. No account, no questions asked: we only email you a link to confirm it was you. This is your right to object under GDPR Article 21.