Planning application · Sligo County Council

Amendments to the permitted but not yet constructed Synchronous Compensator at Ballysumaghan, Sooey

Ballysumaghan, Sooey, Co. Sligo

2560170 · SligoGranted

1.15 ha · Granted · permission to Jul 2030

Planning application 2560170 to Sligo County Council: Amendments to the permitted but not yet constructed Synchronous Compensator grid stabilisation facility granted under Planning Ref: PL22/352, at Ballysumaghan, Sooey. Granted by the council on 19 June 2025. The register gives the permission's end as 21 July 2030.

Timeline

  1. Application lodged
  2. Council granted
  3. Permission ends (date on the register)

The end date is the one the council register states. An extension or a commencement changes it.

Key facts

Reference
2560170
Planning authority
Sligo County Council
Received
2 May 2025
Decided
19 Jun 2025
Status
Granted
Use
Utilities
Site area
1.15 ha

Proposed development

the development will consist of amendments to the permitted but not yet constructed Synchronous Compensator grid stabilisation facility granted under Planning Ref: PL22/352 (Parent Permission). The proposed amendments comprise: a) exclusion of the consented 220kv high voltage gas insulated switchgear (GIS) building and associated compound; and b) a reconfigured and extended high inertia synchronous compensator (HISC) compound containing the consented 1 no. HISC unit enclosed within a steel clad framed style structure (12.1m max height) and all previously consented supporting plant and equipment, additional HV electrical plant and equipment, and all associated and ancillary site works necessary to facilitate the development including: all necessary drainage systems, foundations works, various underground cables and ducts, equipment plinths, internal services roads, rainwater harvesting systems, welfare and office units, material storage containers, compound lighting and palisade gates and fencing, security lighting, CCTV, hardstanding areas and boundary security fence. The remaining elements of the development permitted under Parent Permission Planning Ref: PL22/352 remain unchanged - DEV CONTRIBUTIONS PAID BUT NO COMMEMENCEMENT NOTICE SUBMITTED ON THE BCMS 11/12/2025

Planning status

Permission was granted on 19 Jun 2025. The four-week appeal period has passed with no appeal recorded, so the permission is final. Works can start once a commencement notice is lodged; the register gives its end as 21 Jul 2030.

For the applicant

Is this your application?

Say it is yours and you will see which building firms and trades have asked to work on it, with the contact details they chose to leave. It is free and takes an email address. Nothing is shared with anyone unless you choose to contact them.

Sign in to claim itNo cold calls. Nothing is shared unless you choose to.
Free tool · no account needed

Buying or upgrading a home? Get a free solar, SEAI grant and deep-retrofit report.

Enter an address to see its solar potential, the full SEAI grant it qualifies for, and the BER-uplift economics of a deep retrofit - in one report, in minutes.

Nearby applications

Other applications on the Sligo register close to this address.

All Sligo planning applications

Related

About this page: the facts above come from the statutory public planning register kept by Sligo County Council and are refreshed weekly (last updated 26 Sept 2026). Applicant names and contact details are not shown. Status labels are PlanningLeads' plain-language reading of the register status and the "Use" label is classified by AI from the public description (see how we use AI); neither is legal advice and the council's file is the record. How we handle this data: privacy notice.

Remove my application from this page

If this is your application and you would rather it did not appear here, tell us and we will take the page down. No account, no questions asked: we only email you a link to confirm it was you. This is your right to object under GDPR Article 21.