Planning application · Meath County Council

10 year permission and 35 year operation for a solar farm on two sites

Milltown & Moyagher Lower, Cortown, Kells Co Meath

21396 · MeathOn SiteAppeal decided

121.5 ha · Appeal decided, March 2022

Planning application 21396 to Meath County Council: 10 year permission and 35 year operation for a solar farm on two sites: North Parcel approximately 41.2 hectares, at Milltown & Moyagher Lower, Cortown, Kells. Granted by the council on 31 August 2021; An Coimisiún Pleanála decided the appeal on 28 March 2022. Work commenced on 24 July 2026.

Timeline

  1. Application lodged
  2. Further information requested
  3. Further information received
  4. Council granted
  5. Appealed to An Coimisiún Pleanála
  6. Appeal decided
  7. Work commenced

Key facts

Reference
21396
Planning authority
Meath County Council
Received
2 Mar 2021
Decided
31 Aug 2021
Status
On Site
Use
Utilities
Site area
121.5 ha
Further information requested
26 Apr 2021
Further information received
30 Jun 2021
Commenced
24 Jul 2026
Appeal
ABP - 311460-21 · Appeal decided

Proposed development

the development consists of a 10 year permission and 35 year operation for a solar farm on two sites: North Parcel (Milltown Townland) approximately 41.2 hectares; South Parcel (Moyagher Lower Townland) approximately 80.3 hectares for a total site area of approximately 121.5 hectares. The proposed development on these two sites comprises; Up to 734,000 sq.m of solar photovoltaic panels on ground mounted steel frames, inverter/transformer stations, underground power and communication cables and ducts, boundary security fencing, new internal access tracks, associated drainage infrastructure, new site entrances to the L6835 public local road (North Parcel) and the L8003 public local road (South Parcel), 1 no vehicle passing area on lands adjoining the L6835 local road, CCTV cameras and all associated site services and works. Provision of control building and associated compound within the South Parcel. As part of a separate Strategic Infrastructure Development (SID) planning application, provision of 110KV electrical substation with electrical control building, associated compound with palisade fence and 2 no. overhead line masts, which is to be located within the North Parcel, will be lodged with An Bord Pleanala in due course. A Natura Impact Statement (NIS) will be submitted to the Planning Authority with the Application. Significant Further information/Revised plans submitted on this application

Planning status

An Coimisiún Pleanála concluded the appeal on 28 Mar 2022. The official file has the outcome.

Appeal ABP - 311460-21 on the An Coimisiún Pleanála website ↗

For the applicant

Is this your application?

Say it is yours and you will see which building firms and trades have asked to work on it, with the contact details they chose to leave. It is free and takes an email address. Nothing is shared with anyone unless you choose to contact them.

Sign in to claim itNo cold calls. Nothing is shared unless you choose to.
Free tool · no account needed

Buying or upgrading a home? Get a free solar, SEAI grant and deep-retrofit report.

Enter an address to see its solar potential, the full SEAI grant it qualifies for, and the BER-uplift economics of a deep retrofit - in one report, in minutes.

Nearby applications

Other applications on the Meath register close to this address.

All Meath planning applications

Related

About this page: the facts above come from the statutory public planning register kept by Meath County Council and are refreshed weekly (last updated 30 Sept 2026). Applicant names and contact details are not shown. Status labels are PlanningLeads' plain-language reading of the register status and the "Use" label is classified by AI from the public description (see how we use AI); neither is legal advice and the council's file is the record. How we handle this data: privacy notice.

Remove my application from this page

If this is your application and you would rather it did not appear here, tell us and we will take the page down. No account, no questions asked: we only email you a link to confirm it was you. This is your right to object under GDPR Article 21.