Planning application · Kerry County Council

REDIII: A 10 year planning permission for a solar farm…

Ballyoughtragh South Commons , Farranmanagh Knocknaman and Lisheennashingane (Townlands) , Milltown County Kerry

2560856 · KerryIn AssessmentAppealed
Reference
2560856
Planning authority
Kerry County Council
Received
22 Sept 2025
Decided
11 Aug 2026
Status
In Assessment
Site area
57 ha
Further information requested
19 Dec 2025
Further information received
29 May 2026

Proposed development

REDIII: A 10 year planning permission for a solar farm, 38kV substation and underground cabling grid connection, and energy storage compound with a total area of circa 57 hectares. The proposed development will consist of a solar farm comprising of c.230,000 sq.m of solar photovoltaic panels on ground mounted frames, associated string inverters mounted to rear of panels and 14 no. single storey electrical transformer stations. The energy storage compound will consist of 36 no. containerised energy storage modules and associated plant and equipment, 9 no. transformers and 2 no. auxiliary transformers, 2 no. spare parts containers and 1. no. office unit. Planning permission is also sought for 1 no. 38kV substation and associated electrical compound, including single storey control building, line bay, transformer and accompanying apparatus, and associated grid connection between the proposed substation and Oughtragh 110kV substation comprising 38kV underground electricity cabling of c.3.87km in length to be provided in an excavated trench on private lands and the L11003, L8003 and L80030 public roads, and all associated site development and reinstatement works. The project will also include 33kV underground interconnector electrical cabling within the development site and within the L11003 public road, temporary construction compounds, security fencing, CCTV, access tracks, landscaping (including hedgerow removal and planting), drainage and all ancillary development works and apparatus necessary to facilitate the proposed development. Construction and operational access will be via 6 no. entrances from the L11003 and L80030, with 1 no. of these entrances used for the temporary construction phase only. The operational lifespan of the solar farm will be 40 years and planning permission is requested for this duration. A Natura Impact Statement (NIS) has been prepared and will be submitted to the Planning Authority with the application.

What happens next

The decision has been appealed to An Coimisiún Pleanála. The appeal outcome replaces the council decision.

For the applicant

Is this your application?

Say it is yours and you will see which building firms and trades have asked to work on it, with the contact details they chose to leave. It is free and takes an email address. Nothing is shared with anyone unless you choose to contact them.

Sign in to claim itNo cold calls. Nothing is shared unless you choose to.

About this page: the facts above come from the statutory public planning register kept by Kerry County Council and are refreshed weekly (last updated 2 Sept 2026). Applicant names and contact details are not shown. Status labels are PlanningLeads' plain-language reading of the register status and the "Use" label is classified by AI from the public description (see how we use AI); neither is legal advice and the council's file is the record. How we handle this data: privacy notice.

Remove my application from this page

If this is your application and you would rather it did not appear here, tell us and we will take the page down. No account, no questions asked. This is your right to object under GDPR Article 21.