Within County Cork, the proposed development will consist of refurbishment works…

Between Cahir Substation Ballyhenebery, Co. Tipperary and Knockraha Substation Ballynanelagh, Co. Cork

24/6468 · CorkGranted
Reference
24/6468
Planning authority
Cork County Council
Received
23 Dec 2024
Decided
14 Oct 2025
Status
Granted

Proposed development

Within County Cork, the proposed development will consist of refurbishment works to 39.3km of overhead line, 14 no. steel towers and 204 no. wooden polesets. These lie between Knockraha Substation, in the townland of Ballynenelagh, and the border with County Tipperary in the townland of Glenduff, crossing the County Cork townlands of : Ballynanelagh, Knockraha East, Meeleen, Shanballyreagh, Barnetstown, Mitchellsfort, Meenane, Skahanagh South, Skahanagh North, Coolquane, Scartbarry, Ballyready, Ballyda, Baneena South, Lackabeha East, Hollyhill, Ballinterry, Clykeel South, Ballynanelagh, Clykeel North, Knockauduff, Ballinvarrig West, Kill-Saint-Anne South, Kill-Saint-Anne North, Ballyoran, Glenarousk, Strawhall, Ballyvadona, Carrigabrick, Gearagh, Carrigatoortane, Mountrivers, Moorepark, Ballyderown, Knockanohill, Glansheskin, Kilclogh, Macroney Upper, Castlecooke, Coolaneague, Curraghanolomer, Ballard, Curraghavoe, and Glenduff. The proposed development includes 4 no. temporary construction compounds in the townlands of Moorepark, Ballinvarrig West, Barnetstown, and Skeheen. The works in County Cork will consist of: the replacement ('restringing') of the existing overhead line (OHL) circuit conductor wires; replacement of 7 no. towers and 82 no. polesets with similar dimensions and heights as the existing; installation of 5 no. new towers and 1 new no. poleset at Barrymore Substation and the removal of 2 no. towers; installation of replacement parts on towers and polesets; foundation refurbishment/strengthening and recapping/clearing of shear blocks; all associated site development works, including temporary works areas; clearance of shear block bases; vegetation maintenance works; ancillary site preparation works, site clearance and levelling at the 4 no. temporary construction compounds, temporary works to existing tracks and new temporary access routes to each structure; and all associated works required to facilitate the proposed development. A Natura Impact Statement (NIS) will be submitted to the Planning Authority with the application.

What happens next

Permission was granted on 14 Oct 2025. Third parties may appeal within four weeks; after that the permission is final and works can start once a commencement notice is lodged.

For the applicant

Is this your application?

Say it is yours and you will see which building firms and trades have asked to work on it, with the contact details they chose to leave. It is free and takes an email address. Nothing is shared with anyone unless you choose to contact them.

Sign in to claim itNo cold calls. Nothing is shared unless you choose to.
Free tool · no account needed

Buying or upgrading a home? Get a free solar, SEAI grant and deep-retrofit report.

Enter an address to see its solar potential, the full SEAI grant it qualifies for, and the BER-uplift economics of a deep retrofit - in one report, in minutes.

Nearby applications

Other applications on the Cork register close to this address.

All Cork planning applications

Related

About this page: the facts above come from the statutory public planning register kept by Cork County Council and are refreshed weekly (last updated 21 Sept 2026). Applicant names and contact details are not shown. Status labels are PlanningLeads' plain-language reading of the register status and the "Use" label is classified by AI from the public description (see how we use AI); neither is legal advice and the council's file is the record. How we handle this data: privacy notice.

Remove my application from this page

If this is your application and you would rather it did not appear here, tell us and we will take the page down. No account, no questions asked. This is your right to object under GDPR Article 21.