A 10-year permission for the development at Kellistown East
Kellistown East, Co. Carlow
6.5 ha · Lodged
Planning application 2660287 to Carlow County Council: A 10-year permission for the development, at Kellistown East. A council decision is due by 12 November 2026.
Timeline
- Application lodged
- Council decision due
Key facts
Proposed development
a 10-year permission for the development. The development will consist of the construction of BESS, tail-fed 220kV step-up transformer and all associated ancillary development on ca.6.5 hectare (‘ha’) site consisting of: (i) 210 BESS units each containing six power conversion system units; (ii) 30 static smart transformer stations units; (iii) 60 distribution transformers units; (iv) one auxiliary services building; (v) one office building; (vi) one control building; (vii) one storage building; (viii) one tail-fed 220 kV step-up transformer; (ix) one auxiliary transformer; (x) one Independent Power Producer (‘IPP’) building with two switchgear rooms and auxiliary systems; (xi) one underground firewater retention holding tank (ca.350m³ capacity); (xii) one firewater tank (ca.250m³ capacity); (xiii) one infiltration basin (ca.1,689m³ capacity); (xiv) upgrade works to the existing Site entrance; (xv) internal access tracks between the BESS units, IPP Building and Site entrance; (xvi) underground electrical and communications cabling within private lands; (xvii) one temporary construction compound; (xviii) landscaped berms of up to ca.3m in height; (xix) perimeter security fencing of up to 2.4m in height and security gates; (xx) pole-mounted security cameras; and (xxi) all associated ancillary site development, landscaping and reinstatement works. A 40-year operational life from the date of full commissioning of the entire BESS project is being sought for the proposed development (other than temporary works specified above), and the subsequent decommissioning. A Natura Impact Statement will accompany the planning application
Planning status
The application has been lodged and validated. The council has eight weeks to decide, unless it asks for further information. The council's decision is due by 12 Nov 2026.
Is this your application?
Say it is yours and you will see which building firms and trades have asked to work on it, with the contact details they chose to leave. It is free and takes an email address. Nothing is shared with anyone unless you choose to contact them.
Nearby applications
Other applications on the Carlow register close to this address.
- 2460223in the townland of Kellistown East, County CarlowGranted
of 110kV underground electricity cabling and all associated ancillary site development works. The proposed development of the underground electricity cabling…
- 2560355Kellistown, Tinryland, CarlowGranted
the construction of shed / store used for domestic purposes and storing of vintage vehicles, and all associated site works
Related
About this page: the facts above come from the statutory public planning register kept by Carlow County Council and are refreshed weekly (last updated 5 Oct 2026). Applicant names and contact details are not shown. Status labels are PlanningLeads' plain-language reading of the register status and the "Use" label is classified by AI from the public description (see how we use AI); neither is legal advice and the council's file is the record. How we handle this data: privacy notice.
Remove my application from this page
If this is your application and you would rather it did not appear here, tell us and we will take the page down. No account, no questions asked: we only email you a link to confirm it was you. This is your right to object under GDPR Article 21.