110kVSolarGrid & Substations
110kV Substation and Loop-in connection associated with an approved Solar PV Development.
Scale
110kV
Location
Stokesquater, Painestown, Killary, Ricetown, Castletown K.P., Navan, Co Meath. (www.MillfarmsubstationSID.ie)
Planning authority
Meath County Council
Case type
SID (Not incl LAP SID cases)
Lodged
7 May 2024
Decision
Approve with Conditions · 14 November 2024
Consented under the Strategic Infrastructure Development process by An Coimisiún Pleanála (case 319662). These projects are decided centrally and don't appear in local- authority planning registers.