110kVGrid & Substations

Proposed construction of a 110kV underground grid connection cable connecting the permitted Carrownagowan windfarm to the existing 110kV substation at Ardnacrusha.

Scale
110kV
Location
Within the townlands of Caherhurly, Killokennedy. Cloongaheen West, Leitrim, Castlebank, Ballykeelaun, County Clare. (www.carrownagowangridplanning.ie)
Planning authority
Clare County Council
Case type
SID (Not incl LAP SID cases)
Lodged
20 November 2023
Decision
Approve with Conditions · 23 January 2025

Consented under the Strategic Infrastructure Development process by An Coimisiún Pleanála (case 318505). These projects are decided centrally and don't appear in local- authority planning registers.