Grid & Substations

Proposed development of that portion of an electricity transmission interconnector (Celtic Interconnector) to be constructed onshore in Ireland to the mean high water mark, including a connection to the Irish National Grid, an electricity converter station and all associated and ancillary works.

Location
Townlands of Ballynanelagh, Ballyadam and other various townlands, County Cork.
Planning authority
Cork County Council
Case type
SID (Not incl LAP SID cases)
Lodged
9 July 2021
Decision
Approve with Conditions · 19 May 2022

Consented under the Strategic Infrastructure Development process by An Coimisiún Pleanála (case 310798). These projects are decided centrally and don't appear in local- authority planning registers.