110kVSolarGrid & Substations
110kV electricity substation to connect to and serve a solar farm, associated loop-in infrastructure and all ancillary works.
Scale
110kV
Location
Lysaghtstown, Midleton, Co. Cork.
Planning authority
Cork County Council
Case type
SID (Not incl LAP SID cases)
Lodged
18 December 2020
Decision
Approve with Conditions · 29 June 2021
Consented under the Strategic Infrastructure Development process by An Coimisiún Pleanála (case 308979). These projects are decided centrally and don't appear in local- authority planning registers.