A planting condition works when someone can check it on site. That needs species named in full, sizes and quantities stated, a drawing, a planting season and a period in which failures are replaced. Irish planning law gives the power to require all of that. This guide is for the people who draft these conditions, answer them in a compliance submission, or check them: planning consultants, landscape architects, ecologists and council planners.

6 per metre
Native hedge density
double staggered row, Teagasc guidance
Nov to Mar
Bare root planting season
while the plants are dormant
1 Mar to 31 Aug
Hedge cutting closed period
Wildlife Act 1976, section 40

What a planting condition can require

The power is explicit. Section 34(4)(e) of the Planning and Development Act 2000 lists, among the conditions a permission may carry, conditions requiring the planting, maintenance and replacement of trees, shrubs or other plants, or the landscaping of structures or other land. Maintenance and replacement are in the statute, so a condition can require failed plants to be replaced, and can say for how long.

The Development Management Guidelines for Planning Authorities (2007) set six tests for any condition in section 7.3: it must be necessary, relevant to planning, relevant to the development permitted, enforceable, precise and reasonable. Planting conditions usually fail on the last three. Wording such as native species where possible, or landscaping to the satisfaction of the planning authority, cannot be checked and so cannot be enforced.

Ireland has no national biodiversity net gain requirement, so a percentage gain can only be asked for where the development plan supports it. Sligo's plan for 2024 to 2030 does, in policy P-BD-7, for sites of 0.5 hectares and over.

  • The Planning and Development Act 2024 is being commenced in phases. Check which Act an application falls under before citing a section number.

What a planting schedule must state

The schedule is the document the condition is discharged against. Each line below is something an enforcement officer can count or measure.

ItemWhat to stateWhy it matters
SpeciesThe botanical name and the common name of every plantCommon names are ambiguous: bluebell can mean the native or the Spanish species
ProvenanceWhether native species is enough or Irish provenance is requiredIt decides who can supply the stock, and it is the most common point of dispute
Stock size and formBare root whip, pot size, height band, or girth for standard treesA hedge of whips and a hedge of pot grown plants cost and establish differently
Quantity and densityNumbers per species, plants per metre for hedges, plants per square metre for ground coverWithout numbers, a thin planting still complies
LocationA scaled drawing with each planting area keyed to the scheduleTies the schedule to the site
TimingThe planting season, and the event it follows: commencement, completion or first occupationSets a date after which the condition is breached
ProtectionRabbit guards, stock fencing, and protection of retained trees during worksMost early losses are grazing and damage during construction
Maintenance and replacementThe period, commonly three or five years, and replacement of failures in the next planting seasonSection 34(4)(e) allows it; a condition without it ends at planting day
Three or five years are common periods in Irish landscaping conditions, not a statutory figure. The condition sets its own.

Native species or Irish provenance: say which

Native species and native provenance are different requirements. A native species is one that occurs naturally in Ireland, such as hawthorn or hart's-tongue fern. Provenance is where the seed or parent stock came from. Hawthorn raised in a nursery elsewhere in the EU is a native species and is not of Irish provenance.

The All-Ireland Pollinator Plan's tree planting guidance favours local provenance native trees, because they evolved with native wildlife and locally grown stock carries a lower risk of bringing in pests and disease. That is a reason to ask for provenance where the planting has an ecological purpose: a replaced hedgerow, a woodland edge, a site beside a designated area.

For amenity planting within a scheme, the species is often what matters. Either choice is defensible. What causes trouble is a condition that says native and means provenance, which the developer discovers after the plants are ordered.

  • If provenance is required, say so in the condition and ask for evidence of origin with the compliance submission.
  • If native species is enough, say native species and list them by botanical name.
  • Do not accept a schedule that lists a non-native as native. Cherry laurel, bamboo and Spanish bluebell are the usual ones.

Species by situation

These are native species that suit the planting areas most conditions cover. Match the species to the ground: a schedule that puts sun plants under trees fails in its first summer.

SituationNative species that suit itUsual stock
Boundary and replacement hedgerowHawthorn as the main species, with blackthorn, hazel, holly and guelder roseTwo year old bare root whips
Under trees and on shaded groundHart's-tongue fern, male fern, great wood-rushPot grown, in 9 cm pots
Walls, fences and banksIrish ivy (Hedera hibernica)Pot grown
Meadow and path edgesWild strawberry (Fragaria vesca)Pot grown
Spring interest under treesNative bluebell (Hyacinthoides non-scripta)Bulbs, planted in autumn
A site's own survey comes first. Where an ecologist has recorded the species already on or beside the site, the schedule should follow that record.

Hedgerows: the specification and the calendar

Teagasc's guidance for a new native hedge is a double staggered row of six two year old bare root whips per metre, planted between November and March, with no one species making up more than 70% of the total. Rows and plants are set about 30 centimetres apart. A condition that asks for a replacement hedge can adopt that specification by reference.

Removal is the other half. Section 40 of the Wildlife Act 1976, as amended, makes it an offence to cut, grub, burn or otherwise destroy vegetation growing on uncultivated land between 1 March and 31 August, with exemptions. A hedge that has to come out for an entrance or a sightline is best removed outside that period, and the programme should say so.

The two calendars fit: remove in autumn or winter, plant the replacement in the same dormant season. A condition that allows removal at commencement and planting after completion can leave a gap of two years or more with no hedge. Where the line of the new hedge is clear of the works, ask for it to be planted in the first dormant season after commencement.

A model condition

This wording is an illustration of the points above, to be adapted to the site and the development plan. It is not quoted from any planning authority.

Prior to the commencement of development, the developer shall submit to, and agree in writing with, the planning authority a landscaping scheme comprising a scaled planting plan and a planting schedule. The schedule shall state, for every plant, the botanical name, the stock size and form, the number to be planted and the planting density. All hedging and trees shall be of native species [of Irish provenance, with evidence of origin]. The replacement hedgerow shall be planted as a double staggered row at six plants per metre in the first planting season following commencement. All other planting shall be carried out in the first planting season following completion of the development. Any plant that dies, is removed or becomes seriously damaged or diseased within five years of planting shall be replaced in the next planting season with a plant of the same species and size.

Reason: In the interest of visual amenity and biodiversity.

Checking a compliance submission

A short list for the person who receives the scheme, and for the consultant before it is sent.

  • Every species has a botanical name, and every one is native if the condition says native.
  • Quantities add up: the hedge length on the drawing multiplied by the density equals the number of whips in the schedule.
  • Stock sizes are stated, and they are sizes a nursery sells.
  • The planting dates fall between November and March for bare root stock.
  • Hedge removal is programmed outside 1 March to 31 August.
  • The maintenance period and the replacement duty are written down, with a named party responsible.
  • Where provenance was required, the supplier's statement of origin is attached.

Supplier, same owner as PlanningLeads

Native plants for landscaping and biodiversity conditions

PlantGift.ie supplies Irish native species in packs sized for planting schedules, with free delivery across Ireland. Send a planting schedule or the wording of a condition and it is priced from the packs.

PlantGift.ie has the same owner as PlanningLeads. Its native plants are grown by partner growers in the EU: they are the right species for a native species condition, but if a condition asks for Irish provenance or locally sourced stock, check with the planning authority or the project ecologist before ordering.

Follow the applications and grants in your counties

New applications, decisions and commencement notices across all 31 local authorities, filtered to the counties and scheme sizes you work on.

See pricing

Quick answers

Does a native planting condition require plants grown in Ireland?

Only if it says so. Native species means the plant occurs naturally in Ireland, wherever the stock was raised. Irish provenance means the seed or parent stock is of Irish origin. A condition should say which it requires.

Can a planning condition require dead plants to be replaced?

Yes. Section 34(4)(e) of the Planning and Development Act 2000 allows conditions requiring the planting, maintenance and replacement of trees, shrubs or other plants. The condition should state the period, commonly three or five years.

How many plants per metre does a native hedge need?

Teagasc guidance is six two year old bare root whips per metre in a double staggered row, planted between November and March, with no single species above 70% of the mix.

When can a hedgerow be removed for a development?

It is an offence under section 40 of the Wildlife Act 1976 to cut or destroy vegetation on uncultivated land between 1 March and 31 August, subject to exemptions. Removal is normally programmed for September to February.

Is biodiversity net gain required in Ireland?

Not nationally. Some county development plans promote or require it. Sligo's plan requires development on sites of 0.5 hectares and over to demonstrate a site specific net gain.