Planning application · Cork County Council

Upgrade and extension to the existing biomedicines manufacturing facility,…

Barnahely Ringaskiddy Co.Cork

25/4704 · CorkClosed
Reference
25/4704
Planning authority
Cork County Council
Received
17 Apr 2025
Decided
10 Jun 2025
Status
Closed

Proposed development

Permission for an upgrade and extension to the existing biomedicines manufacturing facility, including: 1) construction of a part single-storey and part two-storey extension to the northern elevation of the existing production building P01 with total floorspace of c. 1,718 sqm and a maximum height of c23.01m, 2) construction of a new medium voltage and low voltage (MV &LV) electrical sub-station with 2 no. single storey over service void building units with total floorspace of c.346sqm and maximum height c.6.33m, and to include a back-up generator, 3) construction of an extension to the existing central utility plant (CUP) to accommodate new boiler, heat pumps and plant rooms with total floorspace of c.482sqm and maximum height to parapet, c.14.2m and to include demolition of an existing boiler house of 68.6sqm, 4) works to upgrade and expand the existing on-site Waste Water Treatment plant (WWTP) incorporating new plant and equipment for increased hydraulic and biological treatment capacity; including a new single storey electrical substation with total floorspace of c.233sqm and maximum height c.5.29m, back-up generator, cooling towers, and odour control unit, 5) all associated site development, landscaping and ancillary works including re-profiling of the earthen berms in the vicinity of the WWTP and associated demolition works, boundary fencing, underground services, high-level pipe and cable racks, internal site roads, yards and temporary construction compounds. This application relates to development, which comprises an activity, which holds an Industrial Emissions Directive Licence (reg. no. P0778-02). An Environmental Impact Assessment Report (EIAR) and Natura Impact Statement (NIS) has been prepared in respect of the development.

What happens next

The council recorded a decision on 10 Jun 2025. The official file has the outcome; a third-party appeal is possible within four weeks of the decision.

For the applicant

Is this your application?

Sign in to follow it through the Cork planning process, get told when the decision lands, and see which builders and trades are working on similar projects near you. It is free and takes an email address.

Follow this applicationNo cold calls. Nothing is shared unless you choose to.

Nearby applications

Other applications on the Cork register close to this address.

All Cork planning applications

About this page: the facts above come from the statutory public planning register kept by Cork County Council and are refreshed weekly (last updated 2 Jul 2026). Applicant names and contact details are not shown. Status labels are PlanningLeads' plain-language reading of the register status and the "Use" label is classified by AI from the public description (see how we use AI); neither is legal advice and the council's file is the record. How we handle this data: privacy notice.

Remove my application from this page

If this is your application and you would rather it did not appear here, tell us and we will take the page down. No account, no questions asked. This is your right to object under GDPR Article 21.